Tender Requirements: 

1.      Technical Details: Please provide all technical details for the equipment before ordering to TIU, to review the quality and specifications. 

2.      Compliance with Ministry of Electricity (MOE) Specifications: Ensure that all equipment, materials, and installations, including SWG, CB, cables, RMU, kiosk, cubicles, panels, etc., are done according to the Ministry of Electricity specifications. 

3.      Load Sharing & Parallel Operation: The generators synchronizing system and step-up transformers should work based on the actual load requirements, enabling load sharing. The step-up transformers should operate in parallel according to the existing load. 

4.      SWG Protection & ATS System: The SWG should have at least 5 protections (short circuit, over current, earth fault, over voltage, under voltage) and an Automatic Transfer Switch (ATS) system with interlock to protect the SWG cells and contents. Step-up transformers should also have protection mechanisms to disconnect from the CB in case of any issues. 

5.      Earthing & Lightning Protection: Ensure that all equipment, materials, and panels are properly earthed and grounded with minimum resistance, following EIC standards. Additionally, install a lightning protection system for the main Substation (S.S). 

6.      Equipment Type: Use SCHNEIDER type RMUs and circuit breakers in the SWG, synchronizing panel, and all other panels. 

7.      SWG Specifications: The SWG should be SM, MODEX-R36, IP3X, and have SF6 breakers. All must meet the acceptance criteria of MOE in Kurdistan. 

8.      Connection of Capacitor Bank Panels: Ensure the consideration of connecting capacitor bank panels for each section when the generators are running. 

9.      Before & After Installation Tests: test should be done for all equipment before and after installation, ensuring their proper functioning, before commissioning the power. 

10.  Guarantees: Provide guarantees for all equipment and installations in the project. 

11.  Maintenance: Maintenance service for all equipment in the project for a period of 1 year including repairing any technical faults that happen. 

   12. Payment Based on Actual Materials and Work Done:  

The payment will be made based on the actual material and equipment installed on-site. Similarly, work wages will be paid according to the real work quantities and distances covered in the project after the completion of all tasks. 

  1. After the installation of all the equipment, 60% of the total payment will be paid. 
  2. Once all the works are completed and approved by the committee, 35% of the total payment will be paid. 
  3. After a year of warranty assistance, along with a committee report confirming the satisfactory performance of the equipment, the remaining 5% of the total payment will be paid. 

Tender Documentation: Include necessary company documents and certifications.

Tender Timeline: 

  • Tender Announcement: [July 20, 2023] 
  • Deadline for Tender Submission: [August 01, 2023] 

Tender Submission: 

Hard copy of the tender proposal, including all required documents in a closed envelope should be submitted to the following address: 

Office No. 140, Main Building, Tishk International University, Erbil, Iraq 

This content has been restricted to logged-in users only. Please log in to view this content.